Block C2

Illustration of Block C2 at The Granges

Block C2

Property Type
Block of flats
Size
1 & 2 bedrooms
Levels
4 levels

In progress45%

Follow the progress of Block C2 from the first brick!

5In progressInternal Fit Out
  1. ScreedCompleted
  2. The first fix: plumbing and electricsCompleted
  3. Closing up the walls and dry liningIn progress
  4. Kitchen InstallationIn progress
  5. Wall TilingTo start
  6. Flooring coveringTo start
  7. Powering upTo start
  8. DecorationTo start
  • Key:
  • To start
  • In progress
  • Completed
Loading video…

Internal Fit Out

Status: in progress

From the outside at least, the buildings will soon begin to look like a finished article. Soon, families will start to move in, but before that, the building needs an interior. There are walls, a roof, and windows, but there is still a good deal of work to be done to prepare for residents.

This milestone includes

Stairs

Start January 2026Expected to end June 2026

Skilled workers will arrive to fit and add fixtures, but they'll need stairs to get that plan off the ground floor.

The first fix: dry lining

Start September 2026Expected to end October 2026

Dry-lining a wall means attaching plasterboard to a wall, which gives a smooth finish to decorate straight away.

Screed

Start July 2026Expected to end July 2026

During this step, a concrete finisher performs a process called screeding. This is cutting off excess wet concrete to bring the top surface of a slab to the proper grade and smoothness.

The first fix: plumbing and electrics

Start September 2026Expected to end October 2026

Now that the building has a structure, workers will install the essential components to make it a home. This includes the electrics, plumbing and ventilation. Part of the first fix is the installation of cables, wires, pipes and other hidden fixtures.

Closing up the walls and dry lining

Start September 2026Expected to end December 2026

Before the second fix, plasterers will carefully close up and finish the interior walls.

Kitchen Installation

Start October 2026Expected to end December 2026

During this process, the team will install the kitchens and internal doors, skirtings and architraves.

The second fix

Start October 2026Expected to end December 2026

As soon as the plasterers and carpenters have completed the dry lining, the skilled workers will return to convert wires into sockets, and pipes into taps.

Wall Tiling

Start November 2026Expected to end December 2026

Tiles will be added to the kitchen and bathroom walls.

Flooring covering

Start November 2026Expected to end December 2026

Powering up

Start November 2026Expected to end November 2026

For the first time the building will be connected to the Grid. Water, gas and electricity will flow through its pipes, and there will be light, heat, hot and cold water.

Decoration

Start December 2026Expected to end January 2027

At this point the painters and decorators will return to add the final touches to the interiors. At this stage, the project is in the final phase of preparation for the first householders. Before we can allow anyone to cross the threshold however, we have our own housekeeping to complete. Stage Five: The completed build.